Investment brief · Magadan Region

Equity participationin the Magadan data center

The project is under construction with planned first-phase commissioning in Q1 2027. AFK Sistema is the lead investor and project sponsor.

Data-center capacity150 MW
01
Firstin Russia
07
Seventhworldwide

How Bitcoin mining works

From a Bitcoin transaction to the miner’s reward in a digital asset.

Bitcoin network flow

From transaction to BTC reward

Mining secures the Bitcoin network and converts computing work into a digital asset.

Bitcoin and fiat currenciesA global network without a national issuer

Bitcoin follows one protocol worldwide and is not the currency of any single country.

Distributed validation
Transactions are confirmed by a distributed network rather than one bank or payment operator.
Predictable issuance
Supply rules are set by the protocol rather than a central issuer.
Global availability
The network runs around the clock for participants worldwide; local rules depend on jurisdiction.
  1. 01Bitcoin transactions

    Users submit transactions to the network.

  2. 02Computing

    ASIC miners compete to find the next block.

  3. 03Block confirmation

    The network accepts the valid computation result.

  4. 04Reward

    The miner receives BTC and transaction fees.

₿
  1. 01
    Bitcoin transactions

    Users submit transactions to the network.

  2. 02
    Computing

    ASIC miners compete to find the next block.

  3. 03
    Block confirmation

    The network accepts the valid computation result.

  4. 04
    Reward

    The miner receives BTC and transaction fees.

Project revenue models

Colocation · proprietary mining · hybrid model

An investor can earn infrastructure revenue or participate directly in BTC mining.

Total project resource150 MW of electrical capacity
Colocation

Mining infrastructure operator

Revenue sources:
  • mining hardware sales
  • client ASIC hosting
  • power supply
  • cooling
  • monitoring
  • repair and maintenance
  • continuous operations
  • 24/7 security
Hybrid modelColocation + proprietary mining
Digital asset

Proprietary mining

Revenue sources:
  • ASIC efficiency
  • BTC mining
  • network fees
  • hardware-efficiency gains
  • changes in the BTC price

The Magadan project supports three models: colocation, proprietary mining, and a hybrid format.

Global Bitcoin mining industry

Key global metrics · Q2 2026

Industrial mining has created a global market for capital-intensive digital infrastructure.

Network scale
≈ 1,067 EH/s
global hashrate
Power base
≈ 17.1 GW
estimated load
Economic scale
≈ $16.9bn
estimated trailing-12-month industry value
Geographic industry concentration65.6% of global hashrate
Top 3
65.6%
Next 12 countries
24.8%
Rest of world
9.6%
Top 3 countriesby share of global hashrate65.6% of global hashrate
  1. 01United States≈ 400 EH/s · 4–5 GW37,5%
  2. 02Russia≈ 175 EH/s · ≈ 2.8 GW16,4%
  3. 03China≈ 125 EH/s · ≈ 2 GW11,7%

The 15 largest countries account for 90.4% of global hashrate. Competition centers on access to power, industrial sites, and professional operations.

Russian Bitcoin mining industry

Key Russian metrics · 2025 and Q2 2026

Russia ranks second globally and is rapidly expanding its industrial mining infrastructure.

02
2nd placeglobally by hashrate share
16,4%
of global hashrate
≈ 175 EH/s
national aggregate hashrate
≈ 2.8 GW
estimated Russian mining load
ёмкость рынка · 2025
RUB 41.17bn
2024 · RUB 33.19bn+24%
power · 2025
2,006 MW
2024 · 1,432 MW+40,1%
hashrate · 2025
125,4 EH/s
2024 · 89,5 EH/s+40,1%

Commercial segment: 13 major operators above 1 MW. Installed and announced capacity totals about 3,352 MW.

Russian mining capacity is growing faster than revenue, reflecting active site construction, stronger competition, and operator consolidation.

Industry growth drivers

Bitcoin network compute capacity grew almost sixfold from 2021 to 2025

Efficient ASICs, industrial data centers, and institutional B2B capital are accelerating industry growth.

Average annual growth in Bitcoin network compute capacity≈ 56% CAGR
  1. 2021
    ≈ 180EH/s
  2. 2022
    ≈ 255EH/s
    CAGR +41,7%
  3. 2023
    ≈ 516EH/s
    CAGR +102,4%
  4. 2024
    ≈ 800EH/s
    CAGR +55%
  5. 2025
    ≈ 1 072EH/s
    CAGR +34%

Energy-efficient ASICs

New chip generations improve hardware energy efficiency

Industrial data centers

computing capacity concentrated at industrial sites

Institutional B2B capital

financing for hardware, power, and operations

  1. More efficient ASICs
  2. More hashrate per MW
  3. Larger data centers
  4. Global network growth

Power and logistics

The isolated, power-surplus Magadan grid provides the project with access to 150 MW

Project power geographyOpen in Yandex Maps ↗
Loading map
1.47 GW
installed capacity of two HPPs
3.014bn kWh
combined generation in 2025
≈ 851 MW
estimated surplus capacity
150 MW
capacity available to the project
Project logistics routeMagadan · Vladivostok · Chinese ports
Loading satellite map
Magadan — Vladivostok
≈ 2,235 km
Shanghai — Vladivostok
≈ 1,609 km
Qingdao — Vladivostok
≈ 1,257 km
Shenzhen — Vladivostok
≈ 2,817 km

Straight-line distances are indicative. Actual transport distance depends on the port, carrier, and delivery route.

Regional advantages

Power · climate · capacity · logistics

Magadan combines low-cost power, a predominantly cold climate, and access to 150 MW.

Electricity cost
Request the rate
individual terms are confirmed in the contractual model
Predominantly cold climate
≈ −2,3 °C
the average annual temperature reduces cooling costs
Capacity available to the project
150 MW
single-site industrial capacity

Isolated power system

The regional system is not connected to Russia’s unified grid and has no external power flows.

Power surplus

Estimated available reserve exceeds 300 MW.

Renewable generation

The Kolyma and Ust-Srednekan HPPs provide about 94% of regional generation.

Power-surplus energy systemThe project’s grid-connection route is contractually secured

Technical profile

Core specifications for the facility, power supply, and operations.

Design capacity
150 MW
Site area
20 ha
Planned commissioning
Q1 2027
Target uptime
98%
01

Scale

150MWDesign capacity
Site area
20 ha
Planned commissioning
Q1 2027
Purpose
industrial Bitcoin mining
02

Power

  1. Generation2 hydropower plants
  2. Grid nodeOrotukan 220/35 kV substation
  3. Distribution35 / 0.4 kV
External supply
independent 220 kV transmission lines
Reliability category
Category III, based on project data
03

Operations

Cooling
air and liquid cooling
Technical team
24/7 with on-site staff accommodation
Repair
on-site warranty repair and service
Security
24/7 armed security
Target uptime98%

Magadan data-center infrastructure

The first phase combines 9 mining halls, 36 water-cooling-ready containers, 37 transformer substations, and an on-site repair and operations center.

Functional zones of the Magadan data-center infrastructure

9 halls and 36 containers

Each hall is designed for 12.5 MW of air-cooled load; each 1 MW container can support water-cooled ASIC configurations.

On-site warranty repair and service

Service is provided by technicians trained to work with leading ASIC manufacturers.

37 transformer substations, 35/0.4 kV

On-site power distribution for data-center buildings and computing load.

Administration, accommodation, and canteen

Facilities support 24/7 technical operations and on-site staff accommodation.

Lead investor and public-sector support

Coat of arms of the Russian Federation
Lead investor and project sponsor

The group contributes capabilities in construction, telecommunications, IT, and large-asset management.

$36.8 bn
assets
FY 2025
$17.0 bn
annual revenue
FY 2025
RusHydro
Energy partner

A party to the agreement covering project delivery and electricity-rate cooperation.

GovernmentMagadan Region
Regional support

Public-sector coordination for project delivery and regional support measures.

01 · Regional government

Support from the Magadan Region

The Magadan Region, AFK Sistema, and RusHydro signed an agreement covering project delivery and electricity-rate cooperation.

02 · Special Economic Zone

A project company has been established as an SEZ participant

The status provides access to tax preferences. The proprietary-mining model may benefit from lower ASIC CAPEX through VAT treatment, subject to applicable requirements.

03 · Energy infrastructure

Grid connection and direct power purchase are secured by contracts

Contracts have been signed with Magadanenergo and RusHydro. Applicable legislation permits bilateral power-purchase agreements with generators.

04 · Priority Development Area

Priority Development Area status is being processed

After approval, the project may apply the tax benefits provided under the regime.

05 · Priority Development Area tax benefits

The preferential regime reduces the tax burden during construction and operations

  • 0% profit tax for the first 5 years; 18% for the following 5 years
  • social insurance contributions at 7.6% for 10 years
  • 0% property tax for 5 years

The lead investor’s capital, the agreement with RusHydro, and regional support measures reduce the project’s infrastructure and tax risks.

Project partners

Hardware manufacturers · Mining pools

The project combines ASIC supply with access to established mining pools.

01

Hardware manufacturers

  • BITMAIN / ANTMINER

    ASIC hardware manufacturing for industrial mining.

  • Canaan / Avalon Miner

    ASIC hardware manufacturing for industrial mining.

  • MicroBT

    ASIC hardware manufacturing for industrial mining.

02

Mining pools

  • ViaBTC

    Preferred mining-pool participation terms.

  • ANTPOOL

    One of the world’s largest mining pools.

  • f2pool

    A major international mining pool.

The project is built around Chinese hardware manufacturers and established mining pools.

Market entry window

The market is positioning for the next post-halving BTC cycle

Current market conditions create an entry window for industrial mining

Bitcoin price growth and correction cycles from 2010 to 2026
  1. 01
    CompletedConcept
  2. 02
    CompletedEngineering
  3. 03
    Current stageActive construction
  4. 04
    January 2027150 MW commissioning
  5. 05
    PlannedCommercial operations
Bitcoin
−52%from ATH

$126 000 → $60 000

4 / 4previous corrections were followed by a new all-time high
Hardware
−53%ASIC price

$8 500 → $4 000

270 TH/sAntminer S21 XP flagship hardware is priced at less than half its previous level
FX window
≈ 75USD/RUB

Two-year low

↓ CAPEXA lower RUB hardware price reduces entry CAPEX; a higher USD/RUB rate supports RUB revenue

Construction is evidenced by active site work

The project is in active construction, including grid connection, building structures, and foundation works.

Grid connection at the Orotukan 220/35 kV substation
Photo 01 / 04Grid connection at the Orotukan 220/35 kV substation
Construction site overview
Photo 02 / 04Construction site overview
Data-center building frame installation
Photo 03 / 04Data-center building frame installation
Foundation earthworks
Photo 04 / 04Foundation earthworks

Investor offer

Make an informed decision after project review

After NDA, the investment manager arranges an in-person review of the documents, financial model, site visit, and participation terms.

  1. 01Execute the NDA
  2. 02Meet the project leadership
  3. 03Review materials in person
  4. 04Discuss the financial model
  5. 05Review contracts, permits, and taxes
  6. 06Visit the site
  7. 07Agree the investment structure
In-person review with the project team

Financial model · power agreements · grid connection · permits · construction budget and schedule · corporate and tax model · participation terms · risk register.

Personal investment review

Request an investment meeting

Менеджер уточнит предполагаемую долю, роль инвестора и требования к проверке. После NDA команда проекта очно представит документы, расчёты и условия участия.

01 · Meeting02 · NDA03 · Materials and calculations04 · Transaction terms
The manager confirms the participation route and arranges a meeting. Confidential materials and calculations are reviewed in person after NDA.

This page is not an offer or individualized investment advice. Returns, valuation, participation size, and exit terms are defined by the documents of the specific transaction.